Commissioners vote Thursday on $1,171,988 for the first Sportsplex design phase. The architect's fee assumes a $100 million project with 12 basketball courts.

The Coral Springs City Commission votes Thursday on a $1,171,988 contract for the first stage of design work on the Sportsplex. The architect’s fee proposal is based on a $100 million project budget.

Updated Nov. 8: the commission approved the contract 2-1 on a voice vote Nov. 5, with Commissioner Joseph McHugh absent, according to the city’s meeting video. Commissioner Shawn Michael Cerra had asked to leave the decision to the new commission. Read our story on the vote.

The city’s Sportsplex project page gives no construction cost.

The item is No. 24 on the agenda for the 6:30 p.m. Thursday meeting at City Hall, 9500 W. Sample Road. The contract, staff summary and fee proposal are on pages 1100 to 1144 of the agenda packet.

What the commission is asked to approve

City staff recommend hiring PBK Architects Florida Inc. of St. Petersburg. The vote would:

  • award $1,171,988 for design up to the 30% milestone
  • let the purchasing manager approve change orders up to $75,000
  • pay for the work from the approved capital budget

Staff said the 30% phase “establishes the overall site layout, facility programming, design concepts, and preliminary cost estimates.” Each later phase would come back to the commission for a separate vote, “contingent upon available funding.”

What the city wants built

Staff said the Parks and Recreation Department wants to develop Tom Messenheimer Field with an indoor sports building and make better use of the Aquatic Complex and Tennis Center.

The city’s call for designers, also in the packet, describes the project in more detail. It lists:

  • a 12-court basketball gymnasium
  • a renovated Aquatic Complex
  • food and drink areas
  • meeting rooms and gathering space
  • training and fitness areas and locker rooms
  • offices and a family entertainment area

The city said the aim is to make the Sportsplex “a premier destination capable of hosting major national tournaments.” The site is at Sportsplex Drive and Royal Palm Boulevard.

The $100 million figure

PBK’s fee proposal is attached to the contract. It says the fee “is based on an assumed $82m construction budget and a $100m project budget.”

The proposal puts the full design fee at $5,859,937 over four phases. Only the first is up for a vote this week.

Bar chart of PBK Architects' proposed Sportsplex design fees by phase: Phase 1, concept and 30% design, $1,171,988; Phase 2, 60% design, $1,464,984; Phase 3, construction documents and bidding, $1,757,981; Phase 4, construction administration and closeout, $1,464,984. Total $5,859,937.
Only Phase 1 is on Thursday's agenda. Chart by Coral Springs Now
Share this chartFacebookWhatsAppX
Phase What it covers Fee
1 Conceptual design and 30% schematic design $1,171,987.40
2 Design development to 60% $1,464,984.25
3 Construction documents, bidding and permitting support $1,757,981.10
4 Construction administration, closeout and as-built plans $1,464,984.25
Total $5,859,937

Design of the aquatics work is listed in the proposal as excluded from the first phase.

The $82 million and $100 million figures are the basis for the architect’s fee. They are not a budget the commission has adopted, and no construction money is on Thursday’s agenda.

How PBK was picked

  • March 26: The city asked firms for letters of interest.
  • April 29: Fifteen proposals were opened.
  • May 27: An evaluation committee shortlisted six firms.
  • June 5: The six presented. The committee ranked PBK first.

The other five on the shortlist were Arquitectonica International, Currie Sowards Aguila Architects, Fawley Bryant Architects, Ohlson Lavoie and The Osborn Engineering Co. Staff said PBK has designed more than 120 sports complexes.

At a June 24 workshop, commissioners reached consensus to let City Manager Catherine Givens “explore opportunities to advance the 30% design plans,” according to the workshop summary in the same packet. In September, commissioners paused the city’s separate master planning contract with Sports Facilities Co., as we reported in October.

What it means for you

  • Nothing is being built yet. This vote pays for layouts, early drawings and the first cost estimates. Those estimates will be the first real test of the $100 million figure.
  • You can speak Thursday. Public comment comes early in the meeting, before the policy items.
  • Later votes decide the rest. Each of the three remaining design phases, and any construction contract, needs its own commission approval.
  • The city still takes ideas on what the building should hold at community@coralsprings.gov.

Our parks and trails guide lists the city’s current sports and recreation facilities. For the people who run each department, see who to call at City Hall.