Coral Springs plans a $150 million membrane plant to replace its lime softening water plant by late 2030. The commission votes Thursday on a $901,347 first contract.
Coral Springs is getting ready to replace the plant that treats its tap water. The city estimates the construction contract alone at about $150 million.
Updated Nov. 8: the commission approved the $901,347 Wharton-Smith preconstruction contract unanimously on a voice vote Nov. 5, according to the city’s meeting video.
The first step is on the City Commission’s agenda for 6:30 p.m. Thursday at City Hall, 9500 W. Sample Road. Item 19 asks the commission to hire Wharton-Smith Inc. of Sanford, Florida, for $901,347. The firm would work with the city’s engineers on cost estimates, scheduling and permits before any building starts.
The details below come from the Nov. 5 agenda and the agenda packet (PDF) (pages 922 to 996), which carries the staff summary, the draft contract and the city’s statement of the work.
What the city wants to build
The new plant would go up on the existing site at 3800 NW 85th Ave. It would replace the current lime softening plant, which keeps running while the new one is built. The city’s statement of the work sets out the plan:
- a new membrane treatment building, using nanofiltration or reverse osmosis
- capacity of 12 million gallons a day
- at first, membrane-treated water blended with lime-softened water
- full membrane treatment by the fourth quarter of 2030
- the lime softening plant shut down after that
The plant must meet current and pending federal drinking water rules, the document says. It names the EPA’s national drinking water standard for PFAS, the man-made chemicals often called “forever chemicals,” along with the lead and copper rule.
The city gives three reasons for switching to membranes. They would end the sludge disposal that lime softening produces, cope with unexpected changes in water quality and deal with emerging contaminants. The water comes from the Biscayne Aquifer, and the plan allows for using the deeper Floridan Aquifer later.
What it costs
The city estimates the construction manager’s total contract, for planning and building, at about $150 million. That figure leaves out the city’s other costs, including design, advisers, site studies and permits. The city says it is looking for federal grants to pay for part of it.
Thursday’s contract covers only the planning phase. The $901,347 breaks down this way:
| Work | Fee |
|---|---|
| Preconstruction progress meetings | $214,573 |
| Producing the guaranteed maximum price | $179,866 |
| Cost estimating | $145,605 |
| Constructability review | $141,580 |
| Allowances | $75,000 |
| Scheduling | $36,668 |
| Value engineering | $24,314 |
| Prequalifying subcontractors | $9,576 |
| Firm’s fee (8.75%) | $65,816 |
| Insurance (1.11%) | $8,349 |
| Total | $901,347 |
When the drawings are finished, Wharton-Smith would give the city a guaranteed maximum price to build the plant. That price comes back to the commission for a separate vote. The city can walk away if the two sides do not agree on it, the draft contract says.
Money for the planning contract comes from the approved capital budget, the staff summary says.
How the firm was chosen
The city asked for proposals July 30 and opened them Sept. 16. Three firms applied:
- Kiewit Water Facilities Florida Co. of Tampa
- OHLA USA Inc. of Miami
- Wharton-Smith Inc. of Sanford
A five-member staff committee interviewed all three Oct. 2 and picked Wharton-Smith. The staff summary says the firm has built membrane plants for Florida cities and has experience keeping an old plant running while a new one comes online. Hazen and Sawyer remains the city’s engineer on the project.
What it means for you
Not everyone in Coral Springs drinks water from this plant. Four providers serve the city. The City of Coral Springs Water District covers Wiles Road south to Royal Palm Boulevard, and north of Wiles from Riverside Drive east to U.S. 441. Coral Springs Improvement District, North Springs Improvement District and Royal Water Works serve the rest. Our who to call at City Hall page lists each one.
- If you are a city water customer: nothing changes at your tap now. The city plans to keep the old plant running until the new one is fully working.
- Water rates: the agenda packet does not say how the plant would affect bills. That question will matter when the guaranteed price comes back for a vote.
- To speak Thursday: submit a written request to the City Clerk before the meeting. The City Clerk’s Office is at 954-344-1065.
The same agenda carries the Sportsplex design contract and the vape shop moratorium extension. We will add the results of the votes when the city publishes them.